Short answer

What is a BOQ for a house? A bill of quantities, or BOQ, is a list of the work items for a building, with a unit and a quantity for each item. A bidder adds a rate and an amount. Each item description should name its material and workmanship, while the full standard of work is in the specification and drawings. Check that the items cover all your work, and ask your engineer to check the quantities.

A hand holding a pencil over a blank ruled tender form, beside a steel tape measure and a stack of drawings on a wooden table
AI-generated illustration: a blank tender-style form, a pencil, a tape and drawings.
On this page (13)
  1. What is a bill of quantities?
  2. What are the columns?
  3. What does an item description include?
  4. Can items be grouped together?
  5. Is my contract item rate or lump sum?
  6. Can the quantities change?
  7. A sample BOQ format
  8. How do I check a priced BOQ?
  9. What mistakes should I avoid?
  10. Who prepares the BOQ?
  11. Frequently asked questions
  12. Related guides
  13. Sources

When you build a house, you hear about a “BOQ” from the contractor, the engineer or a quotation. It is short for bill of quantities. It is a list of the work items for the building, with a unit and a quantity for each one. It is the base for comparing quotes, but it is not a cost estimate on its own. This guide explains what a BOQ is, how to read its columns, and how to check one. It gives no rates, totals or cost ratios. A BOQ for your house must come from your own drawings and specification.

What is a bill of quantities?

The older Indian measurement standard for earthwork, IS 1200 (Part 1):1992, says that bills of quantities “shall fully describe the materials and workmanship, and accurately represent the work to be executed” (clause 2.5). That edition is withdrawn. The current edition was not read for this guide, so the wording above is the older text. The concrete part of the same series, IS 1200 (Part 2):1974, applies the same idea to concrete work.

In plain words, a BOQ says what work is to be done, in what unit, and how much of it. Each item should name its material and workmanship. The full standard of work is in the specification and the drawings. This is practice: a BOQ read on its own can look complete when a key item is missing.

What are the columns?

The columns vary, but a government tender form we read uses these headings. Each bidder fills in the rate and the amount.

ColumnWhat it means
Sl. No.The item number
Item descriptionWhat the work is, with its material and standard of work
Item code or makeA reference or the brand, if the tender names one
QuantityHow much of the item the drawings call for
UnitsThe unit of measure, such as cubic metre or square metre
RateFilled in by the bidder, in figures
Total amountQuantity times rate, including taxes where the tender asks for them
Total in wordsThe total amount written in words

The rate column is blank in the bill you receive from the owner or engineer. The contractor or bidder fills it in. Keep the quantities, units and descriptions the same across all quotes, so that the rates can be compared.

What does an item description include?

An item description can cover more work than its name suggests. The older Indian concrete measurement standard says that, “unless otherwise stated,” the description of an item is held to include, where necessary, “conveyance and delivery, handling, unloading, storing, fabrication, lowering, hoisting, all labour for finishing to required shape and size, setting, fitting and fixing in position, straight cutting and waste, disposal of packings” (IS 1200 (Part 2):1974, clause 2.3). That edition is withdrawn.

So a rate for an item may already cover waste, handling and cutting. Ask whether it does. One tender form we read says “The rate is inclusive of all wastages.” That is one tender’s wording, not a rule for every house.

Can items be grouped together?

Yes, but only in a way that can be traced. The older Part 1 standard, on earthwork, says “Items may be clubbed together provided that the break-up of the clubbed items is agreed to be on the basis of the detailed description of the items stated in this standard” (IS 1200 (Part 1):1992, clause 2.1). This is practice for other work: a lump item is fine only if its split into parts is clear. If it is not clear, you cannot check the quotes.

Is my contract item rate or lump sum?

This depends on how the contract is written. The central government’s procurement manual (updated June 2022) describes these two forms, among others. In an item-rate contract, “contractors are required to quote rate for each individual items of work on the basis of Bill of quantities (BOQ)” (section 3.2.2 (i)). The manual says a lump sum contract suits “stereotype/ repetitive residential buildings or other structures for which standard drawings are normally available” (section 3.2.1 (iv)), where the scope is clearly defined and the risk of change is low.

The same manual says that a schedule of rates “may still be specified in order to regulate the amounts to be added to or deducted from the fixed sum” (section 3.2.1 (v)). This is useful for a house. Even under a lump sum, ask for a schedule of rates for changes. The manual is for central government works, so private homes are not bound by it. It shows how the contract can be written.

Can the quantities change?

Yes. The CPWD Works Manual 2022 defines “Deviation in Quantities” as “Variation in quantities of items of the contract as given in the schedule of quantities and actually executed.” In practice, the final quantities can differ from the bill. Ask how a change is measured and priced before work starts.

A sample BOQ format

The table below is a blank layout. The item list is an example of the kind of items a house needs. It is not a standard format, and it is not a full list for your house. The quantities and units must come from your drawings. The rate and amount columns are for the bidder.

Sl. No.Item descriptionUnitQuantityRateAmount
1Excavation for foundations, including disposal of surplus soilcubic metre
2Lean (plain) concrete under foundationscubic metre
3Reinforced concrete for footings, columns, beams and slab, as per drawings and specificationcubic metre
4Steel reinforcement, as per the bar bending schedulekg
5Brickwork in mortar, as per the specificationcubic metre
6Plastering inside and outside, as per the specificationsquare metre
7Flooring, as per the specificationsquare metre
8Roof waterproofing, as per the specificationsquare metre
9Water supply and drainage pipes and fittings, as per the specificationas stated in the bill
10Electrical wiring and points, as per the specificationas stated in the bill

Where a line needs a quantity, a calculator can help you check the number. The brick quantity calculator and the steel bar weight calculator show the arithmetic with the inputs you choose. Your engineer checks the final figures.

A stack of rolled drawings and a steel tape on a plywood board at a house site
AI-generated illustration: rolled construction drawings and a steel tape on a table at a house site.

How do I check a priced BOQ?

This section is practice. Check each point before you compare quotes.

  • Does every item come from the drawings and the specification?
  • Are waterproofing, grouting, pipes, fittings and finishes listed as separate items, or are they stated as included in another item?
  • Is the unit the same for each item across all quotes?
  • Does the rate include wastage and handling?
  • Is the scope the same in each quote? Two quotes can look different only because one leaves items out.
  • How will changes be measured and priced?

What mistakes should I avoid?

This section is practice.

  • Comparing quotes with different scope. Two rates for the same item mean little if one includes waste and the other does not.
  • Treating an unpriced or priced BOQ as a fixed price without checking what it leaves out.
  • Forgetting wastage, such as broken tiles and cut pipes.
  • Mixing units. Running metres for an item priced per square metre makes the totals wrong.
  • Leaving out hidden items, such as formwork oil, curing water and small hardware, unless the rate covers them.
  • Using old rates when prices have moved since they were written.

Who prepares the BOQ?

This is practice. Sources differ on who should prepare it. A quantity surveyor, an engineer, an architect or a contractor may do so. Ask your architect or engineer, and ask for the BOQ in writing before you compare quotes.

Frequently asked questions

Is a BOQ needed for a small house?

This is practice. A small house does not need a formal tender. Still, a written list of items and quantities from your engineer makes quotes easier to compare.

What is the difference between a BOQ and a cost estimate?

A BOQ lists items, units and quantities. A cost estimate puts a money value on them. The method is explained in how to calculate house construction cost.

Can I use a sample BOQ from the internet?

This is practice. Use it for the layout only. The items and quantities must come from your own drawings. Many online samples include rates, which may not apply to your city, your date or your specification.

Does a BOQ show the quality of the work?

Partly. Each item description should name its material and workmanship, as the older standard asks: the items must “fully describe the materials and workmanship.” The full standard of work is in the specification and the drawings.

This guide is general information. Read the disclaimer. Your engineer and architect decide the quantities and the specification for your house.

Sources

Change log

  • : Added Related guides link to newly published article(s): how-painting-area-is-measured-for-doors-windows-and-grills-is-1200-part-15-coefficients, how-excavation-for-a-house-foundation-is-measured-trench-volume-working-space-lead-and-lift. No other text changed. Approved by the reviewing engineer.